During this second fortnight of July, the renovation of the old fiber cement water supply network with a diameter of 50 mm is being carried out, connecting the pipes from Hospicio Street to the general network on the Rambla de Don Diego, at the entrance to the street.
Mulberry trees.
As well as the placement of new shut-off valves to be able to sectorize the faults.The works will conclude in the coming days with the extension and compaction of hot bituminous mix to cover these areas, framed in the 'Plan Asphalt 2019'.The team has a special decontamination unit for the removal of asbestos, in addition to the protective equipment and security measures against Covid-19.Budget: 19,953.52, VAT included.Responsible company: Construcciones Hermanos Espin, SLU
Source: Ayuntamiento de Alhama de Murcia