The works to improve safety on the Ramblar and Olmillo roads have been awarded (29/07/2020)

The City Council of Alhama de Murcia has recently awarded the works to improve road safety on two roads in the municipality:Way of the RamblarEl Ramblar is a paved road that belongs to the City Council's network of public roads.

It has a length of 2.6 kilometers and has a variable width of 4 to 4.5 meters, on its right edge, Totana-Alhama has a precast concrete channel 40 cm wide (variable), whose function is to carry water irrigation to the different agricultural plots, as well as collecting and evacuating rainwater.The road is traveled by pedestrians who cross it and by vehicles that access its properties.

Having a narrow width makes circulation difficult, creating risky situations, especially in curved sections. The works have been divided into three sections:Section 1, from the intersection of the Ramblar with the Camino de los Tejares to the intersection with the Huerto de la Hormiga path.Section 2, from the junction of the Huerto de la Hormiga path to the junction with the Rambla del Molino.Section 3, from the junction with the Rambla del Molino to the junction with the Almendrico road.The performances are of two types.

On the one hand, the cutting of the chipboard and the demolition of the existing pavement and the canal (if necessary) and the laying on a 10 cm sand bed of a 0.3 meter diameter PVC pipe.

A further 10 cm of protective sand will be placed on top of it and a compacted artificial furrow will be placed on top, in a variable thickness of 15 to 40 cm.

When the thickness is less than 15 cm.

a layer of concrete will be applied.The final firm, 5 cm hot bituminous mixture, will be spread over the compacted gravel.

thick (asphalt).In sections of canal crossing a 60x60 cm concrete chest will be placed.

with a mesh lid.

To collect the rainwater, grids will be placed with a 30 cm precast concrete gutter.

wide, one every 15 meters.To widen the road, the pavement cut, excavation and subsequent filling with compacted and extended concrete have been designed.Olmillo TrailIn the case of the Olmillo road, very similar circumstances occur, with a length of 550 meters and a variable width of the same characteristics as that of the Ramblar. The actions in this case will be similar. Both sections include the placement of new vertical signs and panels.The execution period of the works is two months and the bid price is 70,000 euros.Awarded company: Construcciones y Excavaciones Sánchez López SLU

Source: Ayuntamiento de Alhama de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información