The company Iberdrola has begun works to improve the electrical infrastructure of the urban center, which will result in avoiding prolonged power outages when adverse weather conditions occur, such as those suffered this past year, especially in the south -west of the town.
The works will consist, on the one hand, of laying a new underground line of medium voltage of 20,000 v.
Which will interconnect the transformation centers of the fairground and the one located next to the Cash Lola supermarket in Avda. Ginés Campos.
On the other hand soon, will also undertake works of interconnection of the transformation center called Thyme, located in the urbanization of Calle Tomillo, with the medium voltage airline that provides supply to the urban center at the back of the factory The hole.
These actions will allow supply feedback maneuvers in case of failures.
Source: Ayuntamiento de Alhama de Murcia