The works will be developed during the last week of July and the first two of August, beginning the night of Sunday 23 of July.
The material to be used is white reflective acrylic and reflective acrylic.
To do these work there will be two teams, mainly at night time to minimize discomfort and disruption of road traffic, except the N-340 road that will be made by day.
Parking areas will be marked 48 hours before repainting so that the owners of the vehicles can remove them.
The service contract has been awarded to the company that has submitted the lowest offer, Murseñal, for a total of 26,613.95 euros (VAT included).
Source: Ayuntamiento de Alhama de Murcia