The Councilor for Infrastructure and Public Services, Antonio García, has reported today the works that are carried out in different neighborhoods and districts of Alhama, specifically five actions that are in the implementation phase or that will begin this week .
In the Vidal Abarca street, the drinking water network, the sanitation network, the ones committed to the houses have been renewed and all the pavement has been replaced.
An operation to supply drinking water in Las Flotas has already been completed and, at this moment, the renovation of the partial drinking water network in the district of El Berro is underway;
In La Costera, more than 2 kilometers of supply pipeline will be replaced.
These works have a total completion period of 6 months and will be completed by the beginning of May.
The total amount is 360,000 euros.
The next work that is underway is on Isaac Albéniz street, on the stretch in front of the Health Center.
Before Christmas, the Directorate General of Water executed the renewal of the supply network and its connections, now with the Socamex company, the sanitation network, the connections are being renewed and the pavement is going to be completely replaced.
It has a budget of 52,430 euros.
Today, the renovation of paving of a single platform and replacement of the supply and sanitation networks on Parricas Street has begun.
In addition, a new lighting will be installed that will be attached to the streets on a platform four meters high, with latest generation LED lighting.
Pipelines will also be inserted for the passage of fiber optic cabling and natural gas network.
It has an execution period of 4 months and the budget is 628,030 euros.
Within this street, the two adjacent roads that have no exit are included, where an access to the El Praíco sports complex has been contemplated with new stairs.
The winning company has informed the neighbors, through some indicative signs, that at all times access to your garage will be guaranteed on one side of the street or another.
The traffic will remain cut off and it is foreseen that the access will be covered by Virgen de Los Dolores street, and San Juan and San Antonio streets may also be used, if necessary, towards the center of the town.
The next neighborhood that is under construction is the Carmen, practically completed, from where it will continue to start work that began today in the avenues Spain and Juan Carlos I, to the stretch of intersection with the street Rosario .
They have a deadline of two months and will be completed before the Mayos' party, during the last week of April, trying to reduce the problems they may cause to neighbors as much as possible.
It is planned to run in three phases and will affect the traffic of the municipality, since it is a main artery used by buses and numerous citizens as a way of entry and exit to Murcia or to the center of the municipality.
The budget is 252,000 euros.
It has been decreed the change of use and the signaling of certain routes temporarily, enabling them in two directions of circulation.
Specifically, and initially, will be the following:
- Capitán Portola Street, in the stretch between General García Díaz Street and España Avenue, is enabled in a double sense of circulation.
- Hernán Cortés street, in the stretch between General García Díaz street and España Avenue, is enabled in a double sense of circulation.
José Alfonso Toral, Chief Local Police Officer, has explained the new reconfiguration of traffic, as well as the measures that will be carried out in terms of road safety.
"In the avenue Spain has started phase one, which runs from the intersection from Avenida Antonio Fuertes to Isla de la Gomera street, in which section traffic is completely cut off, the streets that access that first phase, as Captain Portola and Hernán Cortés have been enabled in two ways to facilitate the departure of the neighbors towards General García Díaz Street. "
Toral has highlighted the importance of signals, in order to give the maximum possible information to the residents of Alhama and its visitors in the access to the city center.
"If they come from the Antonio Fuertes avenue, informative signs of circumstantial signs have been placed in the whole lane".
Access to the city center must be made through Cartagena Avenue, Juan Carlos I Avenue and Rambla Don Diego.
In addition to those informative posters that are placed throughout the coming Ginés Campos and Avenida Antonio Fuertes, as well as the entrance by the Cartagena road, others have been placed at the accesses from Sierra Espuña. "
The Chief Police Officer has explained that it is intended to distribute traffic through the rest of the main arteries of the municipality.
"At the intersection on Avenida Cartagena with Avenida Juan Carlos I, as it is the area of ​​maximum affluence, there are already more restrictive signs of prohibited access to certain streets of the avenue Spain, as well as the adjacent streets, which in phase two and phase three will be cut. "
From Local Police, the actions that are going to carry out the agents in the area will focus on controlling that the circumstantial signaling is correctly placed and check that the arteries of passage are free of obstacles.
Toral has appealed to the neighbors "so that as far as possible try not to leave the vehicles in double row and park as correctly as possible, as the incidents that can generate would be remarkable."
Local Police will continue to inform about traffic and road safety, trying to give information every morning from Monday to Friday on the local radio to explain the progress of the works, remembering the evacuation routes to and from the urban center, as well as launch collaboration messages.
Works in execution and already executed:
RENEWAL OF THE NETWORK OF SUPPLY OF PEDANÃAS AND VARIOUS STREETS OF ALHAMA DE MURCIA
Already executed:
- C / Vidal Abarca
- Performance in the Fleet
In action:
- The Costera
- El Berro
Start date of works: already started
Term of execution: 4 months + 2 months
Budget: 360,000 euros
RENEWAL OF SANITATION IN THE ISAAC ALBÉNIZ STREET
Start date of works: already started
Lead time: 1 month
Budget: 62,430 euros
PAVING OF UNIQUE PLATFORM AND RENEWAL OF SUPPLY AND SANITATION IN THE PARRIDES STREET
Start date of works: March 5
Execution period: 4 months
Budget: 628,030.57 euros
RENEWAL OF THE SUPPLY AND SANITATION IN THE BARRIO DEL CARMEN
Start date of works: already started
Lead time: 6 months
Budget: 1,094,838 euros
RENEWAL OF SUPPLY AND SANITATION IN THE AVD.
SPAIN AND JUAN CARLOS I
Start date of works: March 5
Execution term: 2 months
Budget: 252,000 euros
The City Council of Alhama de Murcia apologizes to neighbors and visitors for the inconvenience that may arise during the course of these works.
Source: Ayuntamiento de Alhama de Murcia